Monte Carlo Simulation and Risk Analysis



Proper estimation of the expected NPV of a project normally requires the use of simulation techniques. Simulation is the only simple and generally applicable procedure for overcoming the limitations of sensitivity analysis, calculating the expected NPV, and analyzing risk. Simulation usually requires more information than sensitivity analysis, but the results in terms of improved project design are worth the effort. Proper estimation of the expected NPV requires three steps:

• Specifying the probability distribution of the important uncertain components
• Specifying the correlations between the components
• Combining this information to generate the expected NPV and the underlying probability distribution of project outcomes.

Generating the underlying distribution and calculating the expected NPV through mathematical analysis is generally impossible. The analyst must rely on computer-generated simulations. Using the specified probability distributions of the uncertain project components, the computer simulates as many outcomes as the analyst wishes. In Monte Carlo simulation, the computer acts as if we were implementing the same project hundreds or thousands of times under the specified conditions. Because we assume that some of the project variables are uncertain, the simulated results are different each time. Sometimes the resulting NPV may be negative, sometimes it may be highly positive. The computer pools the results to obtain an estimate of the average result and of its probability distribution. From the simulations, the computer generates a probability distribution for the NPV, including the probability that the project is a failure and the expected NPV. Analysts can readily obtain such software for performing these analyses. Although the techniques are as easy to use as estimating the NPV or IRR of a project, they do require additional information and expert judgment concerning the probability distributions of the critical project components.

Assigning Probability Distributions of Project Components

Assigning probability distributions to project component variables and specifying correlations is the most difficult step. Analysts should base economic analysis on a realistic assessment of costs and benefits, which in turn requires that the estimates of all relevant variables draw on experience in the sector and the country. Quantity forecasts should be based on clearly identified market factors and on experience-based behavioral, technical, financial, institutional, and environmental assumptions.

Analysts can quantify judgment and experience at several levels of sophistication, but even a rather simplified approach is useful in project design. We do not usually need to consider a large number of variables.

Sensitivity analysis can help identify the variables for which probability distributions should be most carefully specified. If, for example, sensitivity analysis shows that the influence of a particular variable is relatively minor, we can treat that variable as if it were certain without introducing large errors. Also, the specification of the probability distribution for a selected variable need not be based on hard data. For example, a large sample of past observations may be available that permits fits against assumed probability distributions, or the analyst may have access to evidence of a more qualitative and subjective nature. The subjective judgments of experienced engineers, financial analysts, and others involved may be valuable in this context.

Finally, if the distributions are unknown, project analysts can also make simplifying assumptions about the probability distribution of variables. One of the simplest and most popular distributions used in empirical risk analysis is the triangular distribution. Three parameters completely describe this distribution: the most likely value (the mode), the lowest possible value, and the highest possible value. The expected value of a triangular distribution is one-third of the sum of the three parameters.


Sunday, September 8, 2013

Risk Analysis of Economic Analysis



The approach also goes beyond sensitivity analysis and switching values for assessing risk. The former estimates how sensitive project outcomes are to changes in the values of critical variables. In a transportation project, for example, sensitivity analysis would indicate to analysts what the effect of a 10 percent decline in traffic on the net present value of the project would be. Switching value analysis identifies the value that a critical variable must assume for the project to become unacceptable. In the transportation example, it would identify the volume of traffic at which the project’s net present value would go to zero. While both techniques are useful in project design, they do not take probabilities or correlations into account, which limits their usefulness. Switching value analysis may tell us that a project will fail if a given variable departs by more than 25 percent from its posited value, but if we do not know the likelihood of this event, the information is of limited use. The major shortcoming of both types of analyses, however, is the disregard for correlation. When one thing goes wrong, something else is likely to go wrong: correlations can be devastating. For example, if projected traffic along a given corridor falters because the expected economic growth failed to materialize, fiscal receipts may also fall short. Consequently, counterpart funds may also be in short supply. Analyzing the impact of one variable at a time may mislead us into believing that risky projects are in fact robust.

Monte Carlo analysis takes into account probabilities and correlations and identifies the likely impact of each variable on project outcomes. It can also take into account delays and other events that may impinge on project outcomes. More important, it helps assess the expected net present value of the project, the probability distribution of the outcome, and the probability of project failure. By ranking the variables in terms of their impact on project outcomes and probability of occurrence, Monte Carlo simulation helps analysts design better projects and identify the variables worth tracking during project performance. Until recently, Monte Carlo simulations were time-consuming, expensive, and difficult. With the advent of personal computers and readily available risk analysis programs, Monte Carlo techniques are as convenient to use as spreadsheets.